Team win: Clemson University Allen N. Reeves Football Operations Complex

The Allen N. Reeves Football Complex, which includes 1.5 acres of outdoor space, supports the day-to-day activities of Clemson University's football players, coaches, and staff. It was constructed in 15 months with zero change orders and within Georgia’s strict cost limitations—a testament to the Building Team’s planning and coordination with owners, staff, and trades.

The Building Team held weekly stakeholder, budget, and BIM coordination meetings over the course of the project’s design and construction. All of the MEP systems were coordinated before anything was installed.

In several instances, the Building Team changed its delivery method to accommodate the budget or compressed scheduling. For example, delays in finalizing the building’s exterior skin pushed releases for its materials several months. To catch up, the procurement process was modified, and design-build and design-assist construction packages were added for several scopes of work. 

Courtesy Thomas Watkins Photography.

To mobilize subcontractors before construction began, the Building Team agreed to run deep foundation as design-build. When the project fell behind schedule, critical-path subcontractors agreed to work six days a week, add second shifts, and increase their manpower.

To match Clemson’s programming needs with the project’s budget, DPR incorporated several new scope items, such as breaking up millwork packages and hiring a second subcontractor to take advantage of available savings with a local cabinet builder. That alone saved $150,000.  

The completed building includes an outdoor basketball shelter, bowling alley, barbershop, production studio, new lockers, sleeping area for players, state-of-the-art training facilities, hydrotherapy pools for injury recovery, and a 25,000-sf weight-lifting room.

Courtesy Thomas Watkins Photography.

Building Team – Submitting firm, construction manager DPR Construction Owner Clemson University Architect Goodwyn, Mills and Cawood Interior architect HOK Structural engineer MMSA MEP engineer RMF Engineering

General Information – Size 142,500 sf Cost $55 million Construction time December 2015 to January 2017 Delivery method CM at risk

Comments

Popular posts from this blog

Construction disputes were slightly less contentious last year

The resolution of global construction disputes remained steady in 2016, and the average time it took to resolve those disputes declined  bit, according to the seventh annual Arcadis Global Construction Disputes Report 2017, which is subtitled “Avoiding the Same Pitfalls.” This report reflects the construction disputes that Arcadis’ team handled around the world. The report infers that the roadblocks to expeditious and less cost dispute resolution often stem from the need for better contract administration, robust documentation, and a proactive approach to risk management. “Our industry contains the best problem solvers in the world,” the report states. “But there often seems to be a lack of ability or willingness of the project participants to compromise and resolve disputes at the earliest and most inexpensive stage possible.” Roy Cooper, Senior Vice President of Arcadis Contract Solutions, attributes disputes to “human emotions that can impede settlements, as they do with phys...

Quick turnaround: Partners HealtchCare

This administrative building, the largest in Somerville, Mass., consolidates 4,500 employees from 14 locations across Boston into one place. The project’s 30-month schedule was half of the typical time frame for such a building. So the Building Team had little margin for delays or mistakes. Twice-weekly meetings that included the client, AEC firms, and consultants were guided by seven core values that served as a roadmap during the design process. Once construction began, project leaders established a risk assessment group that identified and assessed potential problems weekly.  The building creates an “all-under-one-roof” organizational concept and culture, with a training center, multipurpose auditorium (available for use by campus residents, the local community, and the Partners’ network), community hubs, and outdoor spaces that include two acres of green space and walking paths. The facility is near a new subway stop, which connects the building to Somerville’s developing mix...

Green building advocates erect icehouses on Penn. state capitol steps to make point on codes

Advocates aiming to prompt Pennsylvania legislators to update the state’s building codes erected two icehouses on the steps of the state Capitol in Harrisburg to make a point about energy efficiency. One 8-foot-by-8-foot icehouse was built to current code; the other was built to passive house energy efficiency standards. In about three weeks, the project’s designers expect that the half-ton of ice in the less efficient shed will have melted completely, while the block in the high-performance building will still be about half of its original size. Pennsylvania has not updated its energy codes since 2009. Advocates also want state lawmakers to reform the process for adopting new codes. The Senate and House passed bills this spring to revise the state’s building code adoption process. A 2011 law requires an advisory board to approve each code change with a two-thirds vote. Interesting read originally from BDC Network