Seven lessons learned on commissioning projects

Commissioning helps projects achieve greater occupant comfort and satisfaction, higher building energy efficiency, and ensures ease of maintenance for the building engineering staff.

Ultimately, commissioning is where the rubber meets the road in terms of building design. Commissioning a building is how an owner is able to have full confidence that the building is operating as designed and that we aren’t wasting a single dollar on inefficient systems.

Paladino and Company has managed hundreds of commissioning projects including office, hotel, multifamily, schools, and retail; and I have had the opportunity to resolve a range of issues that come along with each opportunity.

I can’t distill everything that we’ve learned, but I can share the common themes and some smart ideas to mitigate typical challenges.

1. The devil is in the details

With mechanical systems commissioning, the contractor’s focus is often on ensuring that all systems meet their basic purpose, which is to provide conditioned air to the space.  What often gets overlooked are the details that may not affect occupant comfort. Consider, for example, systems that provide ventilation that are not working properly. Or something causing a system to use more energy than needed, such as if the schedules are set improperly or if a damper is not functioning. Or components that are intended to prevent or detect failures, such as alarms that are not set up or a leak detector that’s not operating. These are all examples of issues that may not be detected by the end user but will absolutely impact cost and performance.

2. Design for the maintenance team as well as building occupants

Developers and architects often provide as much usable space as possible in the design, without locating mechanical systems in a place that makes maintenance easy. We have seen mechanical units placed above 12-foot-high ceilings with another 8 feet of space between the ceiling and the units. Even a simple task such as changing a filter becomes time consuming, and service on the unit becomes very difficult. When maintenance is difficult, it is less likely that it gets done. Design space so mechanical units can be easily accessed. A smart design saves a lot of time and headache for the operations staff, and improves the maintenance and performance over time.

3. Don’t skip monitoring capabilities

Building engineers have strong feelings about the monitoring capability of their HVAC systems (or lack thereof). A well designed monitoring system that alerts maintenance staff the moment there is a problem can often mean that issues can be identified before there is an adverse impact on the building occupants or harm to equipment. We provide a monitoring and reporting solution called Clarity that has had remarkable ROI – if your building isn’t actively monitored, money could be wasted right now.

4. What you don’t know could cost you

Commissioning unearths problems. Not commissioning a building doesn’t make problems go away – it just allows them to persist and grow, often undetected by building occupants. And the longer the building goes uncommissioned, the more the issues will pile up, creating a big and potentially expensive problem. If your building is using more energy than necessary, has insufficient indoor air quality, or potential safety hazards, you want to know about it sooner rather than later. Property owners should retro-commission their un-commissioned buildings, and do it ASAP. CapEx budgeting season is the perfect time to get bids from commissioning vendors.

5. Enhanced commissioning prevents design headaches

Paladino commissions projects with both fundamental and enhanced commissioning. Possibly the best benefit of enhanced commissioning is the commissioning authority’s design reviews. When a project that only had fundamental commissioning reaches the construction and closeout phases, there are often issues that could have been avoided had we had the chance to review the design and provide feedback to the engineering design consultants. The CxA can use past experiences in the field to identify potential issues in the design. Understanding how things will be installed, controlled, and maintained are critical aspects to the commissioning design review.  Developers should consider the benefits of enhanced commissioning for their projects.

6. Let the design engineer and CxA resolve issues with controls

Let the design enginner and CxA resolve issues with controls.

Control systems can be problematic on complicated projects. The issues usually result from controls contractors designing systems around their own opinions or interpretations. A thorough review of the controls submittal’s sequences of operation, schematics, and wiring diagrams by the design engineer and CxA – and coordination between all parties – will resolve issues and establish a mutual understanding about how the systems will be operated.

7. Test procedures should be reviewed by the persons conducting the tests

It is not uncommon that the person assigned by the contractor to conduct functional performance testing has never reviewed the test procedures, which can lead to having someone onsite with the wrong capabilities or without the appropriate tools, or the system is not fully ready for testing. Effective communication between teams will ensure smooth testing.

Comments

Popular posts from this blog

Construction disputes were slightly less contentious last year

The resolution of global construction disputes remained steady in 2016, and the average time it took to resolve those disputes declined  bit, according to the seventh annual Arcadis Global Construction Disputes Report 2017, which is subtitled “Avoiding the Same Pitfalls.” This report reflects the construction disputes that Arcadis’ team handled around the world. The report infers that the roadblocks to expeditious and less cost dispute resolution often stem from the need for better contract administration, robust documentation, and a proactive approach to risk management. “Our industry contains the best problem solvers in the world,” the report states. “But there often seems to be a lack of ability or willingness of the project participants to compromise and resolve disputes at the earliest and most inexpensive stage possible.” Roy Cooper, Senior Vice President of Arcadis Contract Solutions, attributes disputes to “human emotions that can impede settlements, as they do with phys...

Quick turnaround: Partners HealtchCare

This administrative building, the largest in Somerville, Mass., consolidates 4,500 employees from 14 locations across Boston into one place. The project’s 30-month schedule was half of the typical time frame for such a building. So the Building Team had little margin for delays or mistakes. Twice-weekly meetings that included the client, AEC firms, and consultants were guided by seven core values that served as a roadmap during the design process. Once construction began, project leaders established a risk assessment group that identified and assessed potential problems weekly.  The building creates an “all-under-one-roof” organizational concept and culture, with a training center, multipurpose auditorium (available for use by campus residents, the local community, and the Partners’ network), community hubs, and outdoor spaces that include two acres of green space and walking paths. The facility is near a new subway stop, which connects the building to Somerville’s developing mix...

Green building advocates erect icehouses on Penn. state capitol steps to make point on codes

Advocates aiming to prompt Pennsylvania legislators to update the state’s building codes erected two icehouses on the steps of the state Capitol in Harrisburg to make a point about energy efficiency. One 8-foot-by-8-foot icehouse was built to current code; the other was built to passive house energy efficiency standards. In about three weeks, the project’s designers expect that the half-ton of ice in the less efficient shed will have melted completely, while the block in the high-performance building will still be about half of its original size. Pennsylvania has not updated its energy codes since 2009. Advocates also want state lawmakers to reform the process for adopting new codes. The Senate and House passed bills this spring to revise the state’s building code adoption process. A 2011 law requires an advisory board to approve each code change with a two-thirds vote. Interesting read originally from BDC Network